Why Airport Road Construction Now Runs Through October

October 1, 2026

Drive Airport Road between Cerrillos and the NM 599 interchange right now and you'll hit the same thing you've been hitting since February: cones, a lane shift or two, a stretch of fresh asphalt that ends abruptly where old asphalt picks back up. If you live in Vista Primera, this stretch is your on-ramp to almost everywhere. It is also, eight months in, still not finished.

The city's own capital projects tracker has changed the language since spring. Construction that was originally expected to wrap by the end of August is now projected to run through October. The reason traces back to a sequencing decision the city made to limit how many separate times crews would need to close lanes on this corridor.

What's Left Between Fairly Road and NM 599

The full project is a two-phase repaving of Airport Road, funded by the 2025 GO Bond for road improvements at a cost of $5,497,669.51. Phase 1 covered Cerrillos Road to Fairly Road and was largely done by late April, with restriping and signal-loop detector repairs finishing up through the spring. Phase 2 covers the harder stretch: Fairly Road to NM 599, the exact interchange Vista Primera sits against.

Phase 2 was originally slated to start in early July and run through late August. It's the segment still generating lane shifts and slow-moving machinery notices as of this month, and it's the reason the completion window now reads October rather than August.

Why the City Chose One Long Disruption Over Two Short Ones

Here's the part that doesn't show up in the orange-barrel alerts. Between finishing Phase 1 and starting Phase 2, the city inserted an entirely separate median beautification project, running from late April through June, on the same corridor.

Sequencing it that way was intentional. Parks Division Director Melissa McDonald put it plainly when asked why the city didn't just let the paving crews finish first: "Nothing is more frustrating than to have a roadway project and then a few months later have another median project." The alternative, she said, was to compress both jobs into one extended construction window rather than send crews back to reopen the same road a second time later in the year. "We're really trying to streamline the construction process so that we limit impact to residents."

That's the trade being made on your commute. A shorter, cleaner Phase 2 was available if the medians had been left for a future budget cycle. Instead, Airport Road gets one long disruption instead of two shorter ones spread across different years, which fits with the finish line now sitting in October rather than August.

The Medians Are Not Just Landscaping

The four medians going in between NM 599 and Paseo del Sol West aren't simple grass strips. Parks Division Project Manager Scott Overlie described short walls built from different-colored concrete, gravel, and native plants, with the hardscape designed to channel water toward the plantings rather than let it run off. The material choice is also aimed at reducing how much area is left open for weeds to take hold, which has been a maintenance headache on other city medians.

The more distinctive detail is what might go on top of that hardscape. The Parks Division has been in conversation with the city's Arts and Culture Department about incorporating artwork into the median design. "This really is an art city," Overlie said, "and so we want to recognize and start to be able to showcase some of that."

If that plan holds, the entryway to Vista Primera from the 599 interchange becomes something closer to a public art corridor than a repaved commuter road. That's a different outcome than most residents pictured back in February when the first cones went up.

The Precedent This Sets Down the Road

District 3 Councilor Pilar Faulkner, who represents this part of the city, has been tracking the project through the same public works committee meetings where McDonald and Overlie report progress. Her read on how residents feel about it has shifted over the course of construction:

"We used to get a lot of hate emails and now we get a lot of love emails."

Another resident quoted in the same Santa Fe New Mexican report pointed to what comes next on a nearby corridor: the upcoming reconstruction of Henry Lynch Road is set to include the city's first separated bike lane, cited as a sign that Complete Streets projects are starting to build in bike infrastructure from the design stage rather than adding it after the fact. Airport Road itself doesn't get a separated bike lane in this phase, but the sequencing lesson from this project (do the disruptive work once, do it fully, and build in the extras while the road is already torn up) is the template the city appears to be carrying forward.

Where That Leaves Vista Primera Through October

If you're timing errands or your commute around this, the practical read is straightforward. The Fairly Road to NM 599 segment is where the remaining lane shifts, striping work, and slow-moving equipment will continue to show up through October. Traffic control stays in place for the duration, and the city's Complete Streets Division continues posting week-by-week updates rather than a single fixed reopening date, since weather and field conditions have already pushed the schedule once.

What you get on the other side of it is a repaved corridor that won't need repaving again for years, medians built to actually shed water instead of pooling it, and a real chance that the stretch of Airport Road you drive past NM 599 every day ends up doubling as a small showcase for local art. That's a different kind of finish line than "the potholes are gone," and it's worth knowing that's what the extra weeks bought.

If you want the same kind of specific, sourced read on what's actually changing in Vista Primera and the neighborhoods around it, that's the kind of local reporting Ralph Alan Real Estate Group keeps digging into, not because it's flashy, but because it's the stuff that actually affects how you get around your own neighborhood.